The WSDOT announced recently that the Seattle Tunnel Partners Joint Venture has requested a total of $188 million in change orders so far, and that the Department has denied $157 million of those, with $31 million worth still under review. Among the change orders rejected was one for $125 million plus additional contract time because STP claimed the Bertha TBM was damaged by a steel well casing. WSDOT’s position is that the location of the well casing was included in the contract documents. [Source: WSDOT. Image: Seattle Times Blog]