Hayward Baker will construct their Vibro Piers(TM) foundation system at the new stadium to house the Atlanta Falcons and a new MLS team. Their holes will be 2.5 feet in diameter and 27 feet deep and filled with vibro compacted No. 57 stone. The project is anticipated to take 5 weeks, operating 6 days a week to keep the project schedule on track. Hayward Baker is a sponsor of GeoPrac.net. [Source: Hayward Baker. Image: Hayward Baker]