GeoPrac sponsor Nicholson Construction has started a chemical grouting project in Los Angeles at the Woodrow Wilson Classical High School to treat potentially liquefiable soils beneath the building. This $2 million project is part of a larger $21.1 million project to upgrade the infrastructure in the auditorium and adjacent areas. Nicholson will drill vertical, horizontal and inclined holes at depths of 14 to 24 feet beneath the structure and inject the chemical grout using a Tube-a-Manchette piping system. [Source: Read more about the project from Nicholson Construction. Image: Nicholson Construction]

Pittsburgh, PA – June 2, 2011 – Missouri’s Interstate 44 is considered one of the most frequently traveled highways in the central United States. In early March of 2011, Nicholson Construction was contacted to perform an emergency response grouting operation on the Gasconade Bridge, part of I-44 westbound, over the Gasconade River in Laclede County.