Army Corps Looking for 100 Million Cu Yd of Clay

The US Army Corps of Engineers, New Orleans district is looking for an unprecedented 100 Million Cubic Yards of Clay to be used for reconstruction and fortification of levees in the New Orleans area. Once borrow sources are approved by the Corps, they will likely be contracting directly with a USACOE contractor constructing one of the projects associated with New Orleans Hurricane Protection System.  Material specs are USCS classification of CL or CH, <35% sand, PI < 10, organic content < 9%.

[…]

Project Related

Deleware Forced to Redesign Unfinished Bridge Because of Consolidation Issues

[Update 2/10/08] Updated the name of the bridge. [/Update]

DelDOT is putting the new Indian River Bridge over out to bid. The current bridge is said to be in danger of failing between 2008 and 2012 according to the Army Corps of Engineers, seems to be related to scour. From what I hear, the tidal currents at that inlet being spanned over are tremendous, with water velocities on the order of 35 mph.

In 2005, Mactec, a geotechnical firm, provided a geotechnical report and associated recommendations to DelDOT for how to construct the 45-ft high approach embankments for a 1,400-ft long bridge in light of a 60-ft clay layer (sounds like pre-loading). However, the embankments are not settling as Mactec predicted (not sure if its more or less, probably less meaning slower) and are "shifting laterally" (squeezing?) so the DOT is going with a longer bridge to span the problem soil. More after the break.

[…]